Preparation of modernization of curriculum on use of GIS/RS for DRRM.

1.1 Identification of educational awareness of use of GIS/RS on DRRM in Indian cean Rim

16 weeks

MONTH 01

MONTH 04

1.2 Identification of established best practices in EU countries for DRRM

08 weeks

MONTH 02

MONTH 04

1.3 Workshops on DRRM curricula by EU countries with action plan for WP2 and WP3

04 weeks

MONTH 04

MONTH 04

1.4 Comparative report between EU-IOR practices on DRRM and use of GIS/RS

16 weeks

MONTH 04

MONTH 07

Curricula development and support of capacity building in RS/GIS DRRM.

2.1 Design of train-the-trainer programs on DRRM

24 weeks

MONTH 07

MONTH 12

2.2 Purchase of Equipment for RS/GIS lab for DRRM

48 weeks

MONTH 07

MONTH 18

2.3 Training for innovative teaching methods

32 weeks

MONTH 11

MONTH 18

2.4 Short-term mobilities and internships for teachers in EU

44 weeks

MONTH 09

MONTH 19

2.5 Development of online modules

32 weeks

MONTH 13

MONTH 20

Piloting and Assessment.

3.1 Defining learning outcomes of new or updated curricula in IOR HEIs

32 weeks

MONTH 07

MONTH 14

3.2 Elaboration of course descriptor

44 weeks

MONTH 09

MONTH 19

3.3 Piloting of updated and new courses in Y2 and Y3

 52 weeks

MONTH 21

MONTH 33

3.4 Self-evaluation and peer review for tuning of program

44 weeks

MONTH 26

MONTH 36

Quality Plan

4.1 Development of QA mechanisms for self-evaluation at course level; QAC created to monitor project performance established

12 weeks

MONTH 01

MONTH 03

4.2 Quality reports prepared by WP coordinators and evaluated by the QAC

124 weeks

MONTH 06

MONTH 36

4.3 External Independent monitoring evaluations (mid-term and end)

92 weeks

MONTH 14

MONTH 36

Dissemination & Exploitation

5.1 Development and maintenance of project website and social media

144 weeks

MONTH 01

MONTH 36

5.2 Organisation of promotional material, round tables, national and international conferences

108 weeks

MONTH 10

MONTH 36

5.3 Awareness campaign at Universities and other stakeholders

68 weeks

MONTH 16

MONTH 32

5.4 Establishment of platform for cooperation and delivery of trainings between universities and private sector on use of GIS/RS for DRRM use

68 weeks

MONTH 20

MONTH 36

5.5 Summer schools and short-term courses for agencies and private sector on GIS/RS applications for DRR.

68 weeks

MONTH 20

MONTH 36

Management

6.1 Kick-off meeting and project management meetings

144 weeks

MONTH 01

MONTH 36

6.2 Elaboration and approval of Steering Communication Plan, Dissemination & exploitation plan and creation of project Steering Committee

12 weeks

MONTH 01

MONTH 03

6.3 Project financial and administrative management

144 weeks

MONTH 01

MONTH 36